Daily Schedule
Daily time slots and task statuses for Hansika, Akash and Navakesh. Changes synchronize with the Sprint & Scrum board across devices.
Progress by owner
Task statuses, blockers and sprint records save to shared Cloudflare D1 when connected. Browser changes are kept safely until they sync.
21-Day Calendar
10–30 November 2026 at a glance. Click a working day to open its hour-by-hour plan below. Sundays are off; 10–11 Nov have no recorded progress.
Day & Time Schedule
Every working day hour by hour: Mon–Fri 10:00–19:00, Sat 11:00–19:00, lunch 13:00–14:00, Sundays off. Statuses here and on the board are the same.
Weekly Scrum Task Board
Filter by assignee and move cards through the workflow. Each card has a date, time slot, requirement reference and a clear acceptance condition.
Workflow Coverage
Every workflow in requirement §9 and the tasks that deliver it. WF-27 is built as a disabled action until the owner signs off.
| ID | Workflow | Owners | Dates | Tasks | Progress |
|---|
Daily Scrum (stand-up)
Record what was completed, what is planned today, and blockers. A 10–15 minute check-in at the start of the first block.
Scrum routine for this sprint
Saved stand-ups in this sprint
Weekly Sprint Ceremonies
Planning, review/demo and retrospective notes for the selected sprint.
Rules & Weekly Sprint Alignment
Definition of Done
- Acceptance condition on the card met, with evidence recorded against the workflow ID in the Git issue tracker.
- Code reviewed in a PR by a teammate and merged to develop; staging deploy checked.
- The developer has self-tested it (no testers): authorised completion, returned correction, denied scope, missing settings, stale version, duplicate retry, failed handoff.
- Incomplete work stays open and carries over; never mark Done from the plan alone.
Working hours and capacity
- Mon–Fri 10:00–19:00, Sat 11:00–19:00 (end time is an assumption to confirm), lunch 13:00–14:00, Sundays off.
- Each day: three work blocks plus 18:00–19:00 self-test, commit and PR. Stand-up in the first 15 minutes.
- Limit 141 h per developer for 10–30 Nov; 16 h of it was 10–11 Nov. From 12 Nov each developer has 109 h of tasks + 16 h self-test.
- All 27 workflows fit only because each task is tightly estimated — the 14 Nov review (GR1) checks the pace; if behind, the team lead decides what moves.
Architecture, hosting and Git
- Shared PostgreSQL database for Core, Inventory, PMS, HRMS and P&M with module-owned schemas; Stores writes only its own tables and reads Core through controlled services; no Core configuration editing in Stores.
- React + Vite frontend (Cloudflare Pages), Node.js + Express API on the Hostinger VPS behind Cloudflare; nightly encrypted backups to Cloudflare R2.
- Git: main/develop protected, feature branches, PR + one review, tagged releases, API contracts in Git; secrets never in Git.
- PMS, HRMS and P&M stay on clearly labelled mocks for 30 Nov; a mock is never shown as verified money or identity.
Gates
- G0 · 14 Nov — foundation ready (VPS, DB, backups with tested restore, CI/CD, sign-in).
- GR1 · 14 Nov — re-estimate after Sprint 01 (Mr. Akash + team lead).
- G1 · 19 Nov — Core-routed approvals, MR and PR working end to end.
- G2 · 21 Nov — PR → RFQ → PO → GRN chain working.
- G3 · 28 Nov — all workflows tested, every screen on the API, freeze.
- G4 · 30 Nov — production release v1.0.0.
Open decisions (from the requirement)
- Quarantine release authority (§4.7) — not granted to Inventory Head until assigned.
- Damaged-stock reuse release permission (§4.9).
- PO reopening authority (§5 4.7, WF-27) — action stays disabled.
- Final accounting valuation method for lending (§6 5.5).
- Saturday end time; Core contact for database grants and approval configurations.
How this relates to the existing schedule
- Days, hours, team, hosting, Git, testing rules and the 30 Nov release are taken from the existing schedule (v3).
- Scope now follows the v4 requirement: four privileges, sections 4–8 and workflows WF-01–WF-27.
- Progress, blocked reasons and stand-ups are stored in this browser. Export progress file gives a copy that can be imported on another computer.
- IDs like STR-W2-BE1-03 are planning IDs for this Stores schedule.